Scaffolding and we are almost 3/4 done with the bricks. We went down for a sticky beak on Saturday and found not 1 or 2 but 6 brickys working on our house till 3pm. We were pretty stoked with that as they are only supposed to work till 12MD on Saturdays. Here are some update photos...
Craig and Allison are building a Masterton Villina 28 on Muirfeild Avenue, shell Cove.
Home
Bricks, beautiful bricks
05 March 2012
This week was a really bad week as Monday and Tuesday were the only 2 days it didn't rain. We were very surprised as to how much work actually got done..... Top job bricky!
This week was a really bad week as Monday and Tuesday were the only 2 days it didn't rain. We were very surprised as to how much work actually got done..... Top job bricky!
Windows and plumbing
25 February 2012
Windows and plumbing completed this week. Didn't look very different from the street as it was just the windows but I'm sooooo glad I changed a few windows so they are much bigger on the side we will get all the beautiful views from.
Gas, water (mains and tank), upstairs bathrooms all piped up this week. Bricks delivered Friday and the bricky scheduled to start first thing Monday!!
Windows and plumbing completed this week. Didn't look very different from the street as it was just the windows but I'm sooooo glad I changed a few windows so they are much bigger on the side we will get all the beautiful views from.
Gas, water (mains and tank), upstairs bathrooms all piped up this week. Bricks delivered Friday and the bricky scheduled to start first thing Monday!!